• 0 Posts
  • 2 Comments
Joined 5 months ago
cake
Cake day: June 22nd, 2024

help-circle

  • Well, if your infrastructure is mission critical, then you need one more as spare.

    In this case a new one a qarter mile to the side with a redundant power supply. Mission control could be smack in the center between the launchpads.

    Of course someone®©™ has to make sure, that the whole facility is only utilized in such a way that n-1 launchpads is considered 100% usage.

    Rant/advice over from someone working in a data center, where spare machines are always in use, because someone©®™ said moar power is more important then reliability.